Welcome to Adani Port and Special Economic Zone

Contact Us

Flow Chart for Establishing unit at APSEZ - Mundra

Registration of Business Organization (For new company)
Site visit & meeting with APSEZ Team for proposed project in SEZ
Signing of MOU and payment of Booking Amount to APSEZ
Application to Development Commissioner in Form - F (Copy to APSEZ)
Evalution of the Project at Unit Approval Committee
Issue of Letter of Approval by DC
T1: 45 to 60 -D approval by DC T2: 90 to 120 D if the Proposal put to BOA U/s 9
Submission of Bond - cum - Legal Undertaking (Form - H)
T: 45 -D - *
Apply to DGFT or DC Office for IEC
T: 45 -D - *
Manufacturing units: Application for Registration - cum - Membership Certificate (RCMC)
T: 45 -D - *
Application for GST Registration
T: 50 -D - *
Application to DC for Eligibility Certificate & Exemption of GST for authorized operations
T: 30 -D - *
Application to Development Commissioner in Form - F (Copy to APSEZ)
T: 15 -D
Payment of Balance Amount to APSEZL
T: Immediately after LOA
Plan Approval: Application to Development Committee
T: 45 to 60 -D
Approval of Plan by Development Committee
Issue of Allotment & Possession Letter
T: 15 -D
Application to Development Commissioner in Form - F (Copy to APSEZ)
T:45 to 60 - D
Projects under Category A: Apply to MoEF for EC, Category B: Apply to SEAC, F & ED, GoG (listed in EIA notification dtd 14.09.2006) (Copy of Application to APSEZ)
Other Projects: Application to GPCB for obtaining NOC / CTE (Copy of Application to APSEZ)
Application to F & ED for obtaining CRZ Clearance (if required)
Commencement of Construction on Site
T: 90 to 120 - D after obtaining the CTE.
Consolidated Consent & Authorization from GPCB
T: 60 - D after completion of construction activity.
Application for Power & Water
After Issue of possession letter T1 - 45 - D T2 - 75 - 90 D
Commencement of Operations at SEZ unit
T: 60 - D after obtaining the CTO.

Abbreviations:

T1 - The Required infrastructure facility is already developed for providing connection.
T2 - The required infrastructure needs to be developed for further connection.

* - Simultaneously Applications can be made for obtaining permission.

CTE - Concent to Establish. CTO - Concent to Operate. BOA - Board of Approval.

DC - Development Commissioner | EC - Environment Clearance | GPCB - Gujarat Pollution Control Board | GoG - Government of Gujarat | VAT - Value Added Tax,

APSEZL - Adani Ports and SEZ Ltd. | SEAC - State Level Expert Appraisal Committee, | CRZ - Coastal Regulation Zone, | T - Time Line , D - Days

Obligations of an SEZ Unit:

To achieve positive net foreign exchange earning (NFE).

To provide periodic reports to the Development Commissioner & Zone Customs.

Any Company set up with FDI has to be incorporated under the Indian Companies Act with the Registrar of Companies for undertaking Indian Operations.

To Fulfill the environmental and pollution control norms.

Document for setting up of New Unit

This is a brief Consolidated Application Form-F

Demand Draft of INR 10,000 (DD should be in favor of “Regional Pay & Accounts Officer, Mumbai”, Payable at Gandhidham)

Provisional offer letter of Space issued by Developer, APSEZ.

Complete Project Report

Memorandum and Articles of Association Copy

PAN & GST of Company Copy

Certificate of Incorporation of Firm (Company) Copy

Certificate of Incorporation of Firm (Company) Copy